EN
8 October 2026 - 11:13 AMT

Armenia considers Russia’s nuclear power plant offer: minister

Armenia is discussing Russia’s proposal to build a new nuclear power plant, with a decision expected in 2027, Minister of Territorial Administration and Infrastructure Davit Khudatyan said during an appearance on Public Television.

He added that a decision on the model of the future plant is planned for the first half of next year, after which it will be possible to proceed with clarifying other issues with the country selected to manufacture the plant’s equipment.

“After that, I hope we will move quickly to the construction phase,” the minister said, according to Sputnik Armenia.

He noted that Armenia is examining proposals from several countries, including Russia, the U.S., European countries, China and South Korea.

“We are currently discussing Russia’s proposal, which our team will need to review again. We are studying all the proposals because they differ significantly from one another in economic and structural terms,” he said.

Khudatyan recalled that Armenian authorities had initially focused primarily on the possibility of building a nuclear power plant using small modular reactors, prioritizing projects based on such technologies. However, subsequent developments and changes in energy demand have made it necessary to consider other options as well.

“But now, with developments accelerating rapidly in connection with artificial intelligence factories, energy demand in Armenia has also increased. In other words, while 1.5 to two years ago we had a surplus of electricity, now and going forward, it is no longer possible to have a surplus… It is very important that we make sound economic calculations,” he said.

The minister also addressed the view that the choice of the country to build the new nuclear power plant is driven by political considerations. Khudatyan rejected that assessment, emphasizing that the decision would be based primarily on economic calculations and safety requirements.

“This is an economic issue because we are talking about price proposals that differ by several billion dollars. Whatever cost is determined for the nuclear power plant will be incorporated into electricity tariffs and will have a significant impact on them. Therefore, under no circumstances can we relegate the economic component to a secondary consideration, nor will we do so. The differences in the costs proposed by various countries could affect tariffs by several dozen Armenian drams. That is a luxury Armenia cannot afford. We are not prepared to turn any political consideration into a burden for our citizens, and we will proceed exclusively on the basis of safety and economic factors,” the minister said.

Earlier, Armenian Prime Minister Nikol Pashinyan said that the operating life of the existing Armenian Nuclear Power Plant could be extended until 2046. Such an extension is expected to be carried out in coordination with the International Atomic Energy Agency (IAEA).

The Armenian Nuclear Power Plant accounts for approximately one-third of the electricity generated in Armenia. Its first reactor unit began operating in December 1976, while the second was commissioned in January 1980. Following the devastating Spitak earthquake in 1988, a decision was made to shut down the nuclear power plant, and operations ceased in March 1989. The plant’s second reactor unit was subsequently restarted in November 1995.

Under the original design, the nuclear power plant was scheduled to cease operations in 2016. However, work carried out with the involvement of specialists from Rosatom extended its operating life until 2026. In addition, in December 2023, Rosatom Service and the Armenian Nuclear Power Plant signed a framework agreement providing for the necessary work to extend the operating life of the second reactor unit until 2036.